ERBIL, Kurdistan Region – The Kurdistan Regional Government’s Qushtapa Water Project is moving toward completion earlier than expected, marking a major step in improving water access across Erbil Governorate.
Launched in 2024 under the direction of Prime Minister Masrour Barzani, the project was originally planned for two years. Current progress stands at 81 percent, with delivery expected ahead of schedule.
With a budget of IQD 222 billion, the project is designed to provide clean drinking water and irrigation to Qushtapa and Bestana districts, as well as 72 surrounding villages. Once operational, it will supply 3,000 cubic metres of water per hour, meeting international standards and serving an estimated 240,000 people.
Related: Shaqlawa–Korre Road to Boost Transport Safety and Connectivity
Significant milestones have already been achieved. The intake facility in Qushtapa has been fully completed. Engineers have installed 37 kilometers of 800-millimeter pipeline to the district, along with 263 kilometers of pipelines ranging from 90 to 500 millimeters to connect nearby villages. A 37-kilometer, 33 kV power line has also been completed and is now fully operational.
The Qushtapa Water Project is expected to bring long-term benefits to both households and agriculture, strengthening the water supply network for one of Erbil’s fastest-growing areas.
Source: Kurdistan Regional Government – Department of Media and Information.